Title: Dynamic cost risk estimation and budget misspecification
Authors: Ebbeler, D. H.
Fox, G.
Habib-Agahi, H.
Issue Date: 23-Sep-2003
Citation: AIAA Space 2003
Long Beach, CA, USA
Abstract: Cost risk for new technology development is estimated by explicit stochastic processes. Monte Carlo simulation is used to propagate technology development activity budget changes during the technology development cycle.
URI: http://hdl.handle.net/2014/7711
Appears in Collections:JPL TRS 1992+

Files in This Item:

File SizeFormat
03-1991.pdf3 MBAdobe PDFView/Open

Items in DSpace are protected by copyright, but are furnished with U.S. government purpose use rights.

 

Privacy/Copyright Image Policy Beacon Home Contact Us
NASA Home Page + Div 27
+ JPL Space
Site last updated on November 15, 2012.
If you have any comments or suggestions for this web site, please e-mail Alexander Smith or call 4-4202.